(A) 25
(B) 35
(C) 45
(D) 50
Correct Option is: D
300 male in 50 days do = 1/2work
1 male in 1 day does = ½*1/50*1/300 work
100 male in 120 days do = ½ *1/50*1/300 *100*120 =2/5 work
Total work done = ½ + 2/5 =(5+4)/10=9/10
Remaining work = 1-9/10=1/10
Remaining time = (250-50-120-20)=60days
½ work is done in 50 days by 300 male
1/10 work is done in 60 days by
=300*50*1*2/10*60
=50 male